East Maryville's Commute, Mapped Year by Year to the Pellissippi Extension

November 26, 2026

On the night of July 16, 2026, the Blount County Commission sat through hours of public comment and then voted 14 to 7 to pay the Tennessee Department of Transportation $5 million toward buying land for the Pellissippi Parkway extension. As WATE reported, that money goes toward land and not construction, and construction is set to begin in 2036.

If you're comparing homes on Maryville's east side, along Old Knoxville Highway, Wildwood Road, Brown School Road, Sevierville Road or East Lamar Alexander Parkway, that date affects how you value a house. Every scheduled change to the drive between east Maryville and Knoxville arrives in 2027 or later, and the biggest one is the furthest away. A home there should be priced on the drive it has this week, because that's the drive you'll have for years.

This week: the parkway ends at Old Knoxville Highway

Pellissippi Parkway, State Route 162, currently ends at State Route 33, Old Knoxville Highway. TDOT's own description of the extension starts from "its current terminus at State Route 33." TDOT lists the area's problems on that same project page: a "primarily radial roadway network," no northwest-to-east connection between Alcoa and Maryville, and congestion on US 129, SR 33, US 411 and US 321. If you live off Sevierville Road or near RIO Revolution on East Lamar Alexander Parkway, you reach Knoxville on those roads.

There's also active work on the road that already exists. TDOT's weekly East Tennessee construction report for November 12 to 18, 2026 listed SR 162 between Cusick Road and SR 33 reduced to one lane for bridge work, with possible rolling roadblocks for blasting between 9 a.m. and 3 p.m. The same report listed a new traffic pattern at the northbound Alcoa Highway exit to Cherokee Trail and possible lane closures on US 321 between Woodland Drive and Harmon Road on November 18 and 19. Those notices change every week. If you're timing a test drive from a house to your office, check that week's report before you go, so you know whether a slow trip was the road or a work zone.

Early 2027: Carpenters Grade wraps up on the west side

The first scheduled change is across town. The City of Maryville says Carpenters Grade Road went back to two-way traffic on October 21, and roadway and multi-use path work is still underway, with a contract completion date of January 14, 2027. That project matters if you're comparing an east-side house against one on the west side of town, where the road work will soon be done. Nothing comparable is scheduled on the east side that soon.

Fall 2027: the UT Medical Center end of Alcoa Highway

Alcoa Highway, US 129 and SR 115, is the main route between Blount County and Knoxville and the route to McGhee Tyson Airport. According to WVLT's June 11, 2026 report on TDOT's revised schedule, the section between Cherokee Trail and the University of Tennessee Medical Center is still expected to finish in fall 2027. If you'd commute to UT Medical Center, that's the first date that improves your drive, and it's about a year away.

Spring 2030: the Woodson Drive to Cherokee Trail stretch

The longer Alcoa Highway section moved back. In the same report, WVLT said TDOT now expects the Woodson Drive to Cherokee Trail segment to finish in spring 2030, after engineers found during blasting and excavation near the Woodson Drive interchange that the walls needed more reinforcement. The Daily Times reported that Alcoa Highway improvements have been in the works for 12 years. Two projects are finished, three are in progress, and a final one has been identified for funding within the next 10 years.

If you buy a house this winter and stay five years, you'll probably sell it about the time this work is done. Alcoa Highway will improve while you own the house, but not for most of the time you live there.

FY2036 and later: the Pellissippi extension

TDOT's project page calls the extension "proposed." It would be a four-lane, controlled-access highway with a concrete median barrier from SR 33 to SR 73, East Lamar Alexander Parkway. Right-of-way costs are funded in Fiscal Year 2026, construction is estimated to start in Fiscal Year 2036, and completion is listed as "TBD." The Daily Times reported that the 4.38-mile route crosses Wildwood Road, Brown School Road, Sevierville Road and Davis Ford Road. In later Daily Times coverage, the plan includes an exit on Sevierville Road, US 411, between Nina Delozier Road and Davis Ford Road, and the road would end near RIO Revolution.

The project has been in planning for a long time. A preferred route was chosen in 2012, and the Federal Highway Administration signed the Record of Decision on August 31, 2017. In its 2026 roadway outlook, the Daily Times said construction, "once and if it is able to begin," would take about three to four years and cost $340.2 million, split 80/20 between state and local partners. WBIR quoted TDOT's total estimate at about $372 million. If construction starts in FY2036 and takes three to four years, the extension wouldn't open until near the end of the 2030s.

Even the land-buying phase is a big project. The Daily Times reported that right-of-way acquisition is expected to cost about $75 million before any grading or construction is funded. The local governments' combined share is $11 million: Alcoa approved just over $2 million, Maryville a little under $4 million, and Blount County's portion is the $5 million approved in July. In the same Daily Times story, the Blount Partnership said it supports moving quickly. Citizens Against the Pellissippi Parkway Extension, a local nonprofit, has opposed the project for years and says it will keep doing so. Both positions are on the public record. For a buyer, the takeaway is that the project has a schedule and a long history, and neither one makes the opening date certain.

At the parkway's current end, Pellissippi Place in Alcoa is where Ramston Capital's Pellissippi Lofts apartment project is planned. The City of Alcoa describes it as the research park's first mixed-use development, with apartments, restaurants and retail. When that project was approved, the Daily Times reported that the proposed parkway extension would pass right beside it, near Old Knoxville Highway and Edgewood Acres.

Why this market doesn't require paying for a future road

The regional numbers give buyers room to set their own price. East Tennessee REALTORS' October 2026 Market Pulse reported that in September 2026 the regional median sale price was $375,000, down 1.3% from September 2025, and total housing inventory was up 7.5% over the same period. In September, the sale-to-list ratio held at 98.4%, and 36.8% of homes sold at or above asking. Half went under contract within 32 days, one day slower than a year earlier. These are East Tennessee figures, not Maryville-only numbers. Still, they describe a market where most sellers accept a little less than asking and buyers have more homes to choose from than they did a year ago.

Put that next to the road schedule. A home a few minutes from the planned Sevierville Road exit will be a few minutes from it for at least a decade before the exit exists. If a seller's price counts on the parkway, a September market with rising inventory and most homes selling below asking gives you room to offer based on today's drive.

If you're comparing an east-side home with one on the west side, or with a Knoxville neighborhood, drive each route at the hour you'd actually commute. If the 2027 and 2030 Alcoa Highway dates affect your trip, weigh them too. Treat the extension as a possible benefit you'd get late in your ownership, if at all, and don't pay for it now. If you're looking at land or a home near the planned route itself, check the route maps and documents on TDOT's project page before you make an offer. Then run your monthly costs through our mortgage calculator at the price the current commute supports. If you'd like a sense of the town beyond the roads, our look at downtown Maryville's recent growth and our Maryville neighborhood page cover it.

Quick answers

Is any part of the Pellissippi Parkway extension open? No. TDOT describes it as a proposed extension from SR 33 to SR 73, with construction estimated to start in Fiscal Year 2036 and completion listed as TBD.

What did the July 2026 county vote pay for? Blount County's $5 million goes to TDOT to buy right-of-way, the land needed for the road. It doesn't pay for construction.

When does the Alcoa Highway work finish? TDOT expects the Cherokee Trail to UT Medical Center section to finish in fall 2027 and the Woodson Drive to Cherokee Trail section in spring 2030.

If you're deciding between east Maryville and somewhere else, we're glad to talk through the routes and the road dates with you before you make an offer. If you already own on the east side and want to know how buyers are likely to value your location, Jennifer Scates Group has a free home valuation you can request.